Performance specification
Specifications are written documents that describe the materials and workmanship required for a development. They do not include cost, quantity or drawn information but need to be read alongside other contract documentation such as quantities, schedules and drawings.
Specifications vary considerably depending on the stage to which the design has been developed, ranging from performance (open) specifications that require further design by a contractor or supplier, to prescriptive (closed) specifications where the design is already complete when the project is tendered.
Prescriptive specifications give the client more certainty about the end product when they make their final investment decision (i.e. when they appoint the contractor), whereas a performance specification gives the contractor and suppliers more scope to innovate and adopt cost effective methods of work, potentially offering better value for money.
Typically, performance specifications are written on projects that are straight-forward, standard building types, whereas prescriptive specifications are written for more complex buildings, or buildings where the client has requirements that might not be familiar to contractors and where certainty regarding the exact nature of the completed development is more important to the client.
An exception to this might be a repeat client such as a large retailer, where a specific, branded end result is required and so whilst the building type is well known, the specification is likely to be prescriptive.
In fact, most projects will involve a combination of performance and prescriptive specifications, where items crucial to the design will be specified prescriptively (such as external cladding), whilst less critical items, or items requiring specialist design are specified only by performance (such as service lifts).
Key to deciding whether to specify a component of the building prescriptively or not is considering who is best placed to select that components, i.e. who is most likely to achieve best value, the client, the designers, the contractor or suppliers. Large clients may be able to procure certain products at competitive rates themselves (for example, the government).
Designers may have particular experience of using a specific product (although some clients may not allow designers to specify particular products as they believe it restricts competition and innovation and may relieve the contractor of their liability for 'fitness for purpose').
Performance (open) specifications describe the result that is required from particular items and leave it to the contractor or supplier to satisfy that requirement. In effect it requires the contractor or supplier to complete the design. The nature of the performance required may be defined by the desired outcome, or by reference to standards (in this case it is important to ensure that the standards referred to are up to date, and this can be done by subscribing to services such as NBS).
It is important when defining performance to:
- Ensure that the performance that has been specified cannot be achieved without delivering the desired outcome.
- Ensure the client will be able to test whether the required level of performance has been achieved (i.e. wherever possible the specification should be objective not subjective).
- Require evidence of compliance with the specification (manufacturers test results, calculations, records of tests, provision of samples and mock-ups etc.)
- Ensure that tests and compliance requirements are economically practicable.
- Ensure where there are elements of prescriptive and performance specification that performance items can be properly integrated into the rest of the works.
NB: In the public sector, the government prefers that tendering takes place after the project brief has been prepared, i.e. before any design studies have been undertaken. Tenders are based on an output-based specification setting out only the functional requirements for the development and not prescribing how those requirements should be achieved.
However, as the public sector tends to procure repeat building types such as schools, hospitals, prisons etc. there are a great number of existing standards and codes that specifications can refer to.
The Geospatial Glossary, published by the Geospatial Commission, and accessed on 17 September 2022, defines an open specification as: ‘A specification that promotes interoperability through its public availability to developers, who use it to develop software or hardware compatible with the common resource described in the specification. Open specifications are generally consistent with related standards and are updated to conform with new standards and new technologies. They may be developed and maintained, as in the case of OpenGIS Specifications, by a public open consensus process.’
[edit] Related articles on Designing Buildings
- Contractor's designed portion.
- Final specifications.
- Insulation specification.
- Outline specification.
- Output-based specification.
- Performance.
- Prescriptive specification.
- Production information.
- Project brief.
- Public procurement.
- Service level specification.
- Specification.
- Specification basics.
- Tender.
- Track record.
[edit] External references
- The JCT Guide to the Use of Performance Specifications.
- NBS: Briefs 4. Prescription or performance.
- OGC: Whole-life costing and cost management.
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.
























Comments